Prior to lifting the slump mold, concrete must be removed from _____.

Prepare for the PCC Level 1 Test with customizable quizzes. Use our study tools with detailed explanations to ensure you're ready to excel on the exam!

Multiple Choice

Prior to lifting the slump mold, concrete must be removed from _____.

Explanation:
The concrete around the base of the mold must be cleared before lifting. This ensures a clean release: if concrete sticks to or surrounds the bottom edge, the mold may cling or drag during lifting, which can bias the measured slump. Clearing the area around the base prevents this interference and gives an accurate, true subsidence value. Removing concrete around the top surface or inside the mold would disturb the sample or isn’t necessary for a proper release, and cleaning the outside of the mold isn’t the critical step for a clean lift.

The concrete around the base of the mold must be cleared before lifting. This ensures a clean release: if concrete sticks to or surrounds the bottom edge, the mold may cling or drag during lifting, which can bias the measured slump. Clearing the area around the base prevents this interference and gives an accurate, true subsidence value. Removing concrete around the top surface or inside the mold would disturb the sample or isn’t necessary for a proper release, and cleaning the outside of the mold isn’t the critical step for a clean lift.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy